With the aim of boosting supply of  electricity for the increasing population of townships in Mandalay District, a new transformer was installed at Aungpinle Main Power Station as of 20 November, 2014
The 132/33/11 KV (30) MVA transformer, which supplies electricity to Chanmyathazi, Aungmyethazan and Patheingyi townships, replaces a 132/33 KV (3×5) MVA one installed there 12 years ago. Electricians of Myanma Electric Power Enterprise who carried out the installation work subsequently linked up power lines, enabling the power station to supply 11 megawatts of electricity to the three townships, compared with only 5 MW before.–Ministry of Electric Power