Power supply expands in Yangon eastern district townships

FB IMG 1739438408746 sskm
Repair works underway at the Shweli-Mangsi 230 kV transmission line.

As of 13 February, the power supply schedule has been extended to a four-hour on, and four-hour off scheme in Yangon Eastern District, which includes Tamway Township, South Okkala Township, Dagon Myothit (Seikkan) Township, Dagon Myothit (South) Township, Dagon Myothit (North) Township, Dagon Myothit (East) Township, Dawbon Township, Pazundaung Township, Botahtaung Township, Mingala Taungnyunt Township, North Okkalapa Township, Yankin Township, Thingangyun Township and Thakayta Township, from the previous four-hour on and eight-hour off schedule.
The four-hour on, four-hour off scheme was back in Yangon Western District on 3 February after the 230 kV Shweli-Mangsi transmission line was repaired.
“Of two Shweli-Mangsi transmission lines, the 230 kV line was repaired but the other one, which also has 350-400 megawatts, has yet to be repaired due to the security concern,” said an official from the Ministry of Electric Power. — Htun Htun/ZS

Share this post
Hot News
Hot News